Hi, David,
What I want to say is:
- We cannot use anymore the info record. So we will delete it.
- Actually the material cost calculation use the info record.
My question is: What I need to change in the configurations about the costs calculation?
Just for your understanding: Our cost calculation use the info record when we don't have any PO. When the material is new. And, many times, this material has a expressive value. So me need to consider this.
When is just a row material, we have the option of using the "planned price 1" in "Costin 2" in the MM02 (There ar 3 options in OKKN: material, info record and PO).
But when the material is a "Subcontracting" the only option in OKKN is the info record and the PO.
Thanks
Evelyn