Re: Changes in Active Query of POWL
Hi Ankita, Within standard POWL, you need to find the appropriate text (with portal role) which is appearing on portal to identify the correct application under which the queries are registered. Then...
View ArticleRe: Changes in Active Query of POWL
Hi Ankita, Go to transaction POWL_COCKPIT and look for the corresponding application ID. 1) Within a application ID there will be n number of queries registered. You have the choice to delete the...
View ArticleRe: UWL is not showing New and In Progress tasks
Hi, Please check1) if your user is not locked or expired in backend and task are present in SBWP backend inbox.,check UWL connection status from UWL itself,2) Check UWL NWA destinations starting with...
View ArticleBackend error : enter plant
Hello Experts, We are running on SRM 7.0 SP12, We have an issue while ordering the PO after all the approval's and when the system tries to transfer the PO to ECCwe have an error "Backend error : enter...
View ArticleRe: Unable to maintain Language translations for UOM
Hi Anil, Pls follow the below steps. Go to Tcode SE63 Go to menu --> Translation --> Abap objects --> Short textsExpand Meta Objects and select TABL Tables (Meta) Now in object name press F4...
View ArticleRe: SRM PR,PO is not getting created in ECC backend
Hi Elham, Please check your org structure(ppoma_bbp), did you assigned company code to your purchasing organization?Are there multiple purchasing organization's in the org structure?...
View ArticleRe: Update cart business partner(s).
Hello Stacy, But it would only help you to change in PO not in SC. And I guess you are looking for SC.I do have a Z-report which helps me to change the Requestor for PO. ThanksGaurav Gautan
View ArticleSRM 7 EHP3 : BSP SUS Screens
hi,We are running the SUS-MM in portal 7.03. Html UI element such as Button or table are not displaying:Any idea? Regards,Joseph
View ArticleRe: Unable to maintain Language translations for UOM
Hi Anil, Thanks, this worked. I could maintain the translations in table T006A, But in TR we have few more tables like T006B, T006C, T006D and T006T in which language translations are missing when...
View ArticleRe: Unable to maintain Language translations for UOM
Hi Bansal, Add these into local object and create a TR. Best Regards,Anil
View ArticleRe: Change PO's currency
Hello Dev, I found the document very interesting.In my case, canada and USA belong to the same NPP organization and the currency of the supplier is USD.When canadian create SC with currency CAD. it...
View ArticleRe: Change PO's currency
Yes. You can use different currency as per plant via vendor sub-range.You will get all details in this document.it will be very much better if you try the same in your practice client and revert back...
View ArticleRe: SRM 7 EHP3 : BSP SUS Screens
Hi,I resolve the problem with oss note1874278 - Error 'thtmlbccelleratormanager is undefined' in the SUS start page Joseph
View ArticleRe: UWL is not showing New and In Progress tasks
Hi Siddharth, Thank you very much for providing the assistance. I would like to confirm that we have tried with all the suggestions and there is no luck Best Regards,Bharathi
View ArticleRe: Substitute Team Carts are not available in the POWL
Hi Laurent, Thank you very much for your swift response. We are in SRM 7 EHP 3. Could you please advise whether the note is still valid for that as the note validity is still 702 only. Thanks in...
View ArticleRe: UWL is not showing New and In Progress tasks
Hello Bharathi, if all kinds of task WI are displayed in user's SBWP, it means there is a connector problem between EP and SRM.Check with an EP consultant.Regards.Laurent.
View ArticleRe: Substitute Team Carts are not available in the POWL
Hello, i do not have the answer.Check with SAP by raising an OSS message. Regards. Laurent.
View ArticleRe: Substitute Team Carts are not available in the POWL
Thank you Laurent for the update and I will keep you posted about the SAP response. Best Regards,Bharathi
View ArticleRe: UWL is not showing New and In Progress tasks
Hi Laurent, Thanks for your suggestion. The strange thing is, if an action has happened on the work item, then it is appearing in UWL. But if there is no action, then it is not appearing. For example,...
View ArticleRe: UWL is not showing New and In Progress tasks
Hello, do not know: this is an EP issue, so check with an EP consultant... You can also have a look at below KBA:2032202 - First access to UWL doesn’t show up to date work items1993994 - MSS/ESS UWL...
View Article